During the Executing and the Monitoring and Controlling phases, the project sponsor tells you, the project manager, that the requirements have changed for one of the project deliverables. Based on this new knowledge, you have to complete additional planning. What is the term used to describe this series of events?

  1. Regression testing
  2. Progressive planning
  3. Progressive elaboration
  4. Project elaboration

The correct answer is 3.

Regression testing has nothing to do with this question. Progressive planning and project elaboration may sound correct, but they are not applicable in this situation.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Leave your response!

Add your comment below, or trackback from your own site. You can also subscribe to these comments via RSS.

Be nice. Keep it clean. Stay on topic. No spam.

You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

This is a Gravatar-enabled weblog. To get your own globally-recognized-avatar, please register at Gravatar.