Your company has undertaken a quality program that focuses on involving everyone in the organization, manager and workers, in an integrated effort toward continuous improvement at every level. Which program is this?

  1. Six Sigma
  2. TQM (Total Quality Management)
  3. QFD (Quality Function Deployment)
  4. ISO9000

 

The correct answer is 2.

The scenario in the question describes Total Quality Management; therefore, TQM is correct. TQM is a process that encourages companies and employees to focus on continuous improvement, thereby improving the quality of their business practices and products.

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading...Loading...

Leave your response!

Add your comment below, or trackback from your own site. You can also subscribe to these comments via RSS.

Be nice. Keep it clean. Stay on topic. No spam.

You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

This is a Gravatar-enabled weblog. To get your own globally-recognized-avatar, please register at Gravatar.