You are managing a process improvement project that is attempting to improve the efficiency of technical processes for offshore drilling operations. Which quality control tool would you use to determine if there was a relationship between the length of the team’s work shifts and the number of safety incidents reported?

  1. Control chart
  2. Run chart
  3. Scatter diagram
  4. Pareto chart

The correct answer is 3.

Scatter diagram is the correct answer because scatter diagrams plot two variables, which are called the independent variable and dependent variable, to show the relationship between them. By plotting these two variables, you can graphically show the relationship between two variables.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading...Loading...

Leave your response!

Add your comment below, or trackback from your own site. You can also subscribe to these comments via RSS.

Be nice. Keep it clean. Stay on topic. No spam.

You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

This is a Gravatar-enabled weblog. To get your own globally-recognized-avatar, please register at Gravatar.