PMP Question of the Week: Project Cost Management

pmpweek05Which of the following is not a process you will complete during Project Cost Management?

A. Estimate costs
B. Determine budget
C. Control costs
D. Determine critical path

The correct answer is D.

Determining the critical path is a Project Time Management process. Answers A, B and C are all processes of Project Cost Management.