PMP Question of the Week: Breakdown Structures

pmpweek07Various breakdown structures can be used on a project, such as the work breakdown structure. Which of the following is not a structure identified in A Guide to the Project Management Body of Knowledge (PMBOK® Guide)?

A. Risk breakdown structure
B. Resource breakdown structure
C. Organizational breakdown structure
D. Timeline breakdown structure

The correct answer is D.

There is no such thing as a timeline breakdown structure. Answers A, B and C are all identified in the PMBOK® Guide.