PMP Question of the Week: Outlining Project Roles

pmpweek05You want to graphically outline project roles and responsibilities. Which tool should you use?

A. Resource Assignment Matrix (RAM)
B. Responsibility Assignment Matrix (RAM)
C. Responsibility Assignment Grid (RAG)
D. Resource Assignment Chart (RAC)

 

The correct answer is B.

Answer A is incorrect because of the use of the word resource. Answer C is incorrect because of the use of the word grid, and answer D is incorrect because the tool needed in this scenario is a matrix, not a chart.