PMP Question of the Week: Stakeholder Register

pmpweek05

You are completing a stakeholder register. To what process group does this activity belong?

A. Closing
B. Monitoring and Controlling
C. Initiating
D. Executing

The correct answer is C.

The Initiating Process Group is made up of only two processes: Develop Project Charter (in the Project Integration Management Knowledge Area) and Identify Stakeholders (in the Project Communications Management Knowledge Area).

Related Resources
PMP Exam Prep Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

In this article

Join the Conversation