PMP Question of the Week: Perform Quality Assurance

pmpweek07

You are conducting the Perform Quality Assurance process to ensure that quality standards have been properly used. To which process group does this process belong?

A.  Planning
B. Monitoring and Controlling
C. Closing
D. Executing

The correct answer is D.

Answer D is correct. Perform Quality Assurance is the only process in Project Quality Management under the Executing process group.