You are conducting a make-or-buy analysis to determine whether your project team should test the new software they are creating, or if testing services should be purchased from outside sources. Which of the following are not criteria you should consider?

  1. Budget estimates
  2. Direct costs
  3. Technical differences
  4. Indirect costs

The correct answer is 3.

Answers A, B, and D are included in make-or-buy analysis.