PMP Exam Prep Question of the Week

Progressive elaboration means that the ability to provide detailed information about project constraints, issues, needs, requirements, etc., ___________ as work on the project progresses (continues).

  1. Decreases
  2. Does not change
  3. Increases
  4. None of the above

The correct answer is 3.

The project is developed in a step-by-step, incremental fashion. Progressive elaboration means that you learn more about the project as you do the work of the project, and as time goes by.