PMP® Exam Prep Question of the Week

The project scope statement is considered one of the foundational documents of project planning. Which other document is also considered to be one of the foundational documents of project planning?

  1. WBS (work breakdown structure)
  2. SOW (statement of work)
  3. Preliminary project scope statement
  4. Historical record of fact

The correct answer is 1.

The WBS is correct because the “WBS provides a deliverable-oriented decomposition of project work that defines the total scope of the project.” The preliminary project scope statement is not included in the A Guide to the Project Management Body of Knowledge—Fifth Edition (PMBOK® Guide) and the other two answers are distractors.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

 

Registered trademarks of the Project Management Institute, Inc.:
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP, PMBOK, and the PMI Registered Education Provider logo

In this article

Join the Conversation