When is a project complete?

  1. When the team is disbanded
  2. When a party has been held to celebrate the completion of the project
  3. When management declares the project over
  4. When formal acceptance is received


The correct answer is 4.

When formal acceptance is received is correct because Verify Scope is the process of formalizing acceptance of project deliverables, including the end deliverable. Acceptance via Verify Scope process is an input to Close Project or Phase process.