Which of the following is not a component of the Close Project or Phase process?

  1. Confirm that the project or phase has met all the requirements of the customer or sponsor.
  2. Close procurements.
  3. Verify that all deliverables have been validated and accepted.
  4. Collect project or phase records.

 

The correct answer is 2.

Close procurements is the only answer that is not part of the Close Project or Phase process. The remaining answers are components of this process.