A PMP receives a contract from a client to manage a software development project. The PMP discovers that 25 percent of the software developers are also contractors and none of them have legal software licenses. What should the PMP do?

  1. Report this vi+C8olation to the PMI.
  2. Report this violation to the company’s senior management.
  3. Fill out a Software Violation Report.
  4. Report this violation to the software association.

 

The correct answer is 2.

The PMI® Code of Ethics in the chapter on responsibility states that the project manager has the responsibility to notify appropriate authorities of any violations of regulation or law.