What does an SPI of 1 mean?

  1. The project is on schedule
  2. The project is on budget
  3. The project is ahead of schedule
  4. The project has only one CP

 

The correct answer is 1.

The project is on budget is a cost evaluation and The project is ahead of schedule would require an SPI of greater than 1.  The project has only one CP is also not correct because SPI has nothing to do with the CP.