PMP Exam Prep Question of the Week

You have just compiled a short list of qualified sellers based upon preliminary proposals. Which process are you performing?

  1. Plan Procurements
  2. Conduct Procurement
  3. Administer Procurements
  4. Close Procurements

 

The correct answer is 1.

The qualified seller list is an output of Plan Procurements. It is an input to Conduct procurement, which occurs before answers Administer and Close Procurements.