Which of the following is not one of the sources of project conflict?

  1. Schedule
  2. Management approach
  3. Resources
  4. Administrative process

 

The correct answer is 2.

Although Management approach can be a source of conflict, it is not one of the sources listed by the PMI. The complete list of sources of conflict mentioned by the PMI includes scarce resources, schedule priorities, and personal work styles.